Work at Nicolet High School continues to make great progress as we work our way throughout the building.

Over Spring Break, you would have noticed the existing front canopy was removed. Over the last in-service day, we took advantage of the great weather to set the steel for the new entrance to Nicolet High School!

In the Athletic Wing of the Building, finishes are starting to be installed with the epoxy floors and the ceramic tile being installed. In a few short weeks these locker rooms will be complete! Over in the Fitness Center, we are wrapping up with steel stud framing and after inspection we will be starting the drywall process.

In the Upper Math and Science Classrooms, we continue chipping away at turning over classrooms ahead of the busy summer! We are wrapping up the second to last move of the school year in the Math Wing. In the next week we will be turning over another Science Classroom as well.

Find the latest Executive Summary by visiting: 